Project Update: Tower 42 Level 12 Leaves A & B

J&C Architectural are proud to confirm we are nearing the completion of another floor of our internal office fitout works at the Tower 42 building (ex-Natwest Tower) in London.

Level 12, Leaves A & B are nearing completion with the final touches to the Managing Director’s Office glazing and snagging remaining in Leaf B. The Tenant is now occupying Leaf A and FF&E installation is in progress for final handover of Level 12 later this week.

If J&C can be of assistance to your next fit out project, please get in touch.

 